Skip to main content

San Juan Creek Bridge Replacement Project

Construction Updates

The Orange County Transportation Authority (OCTA), in coordination with Metrolink, is replacing the railroad bridge over San Juan Creek. Built in 1917, the bridge has reached the end of its useful life and will be replaced by a new three-span girder bridge.

Project Details

SJC Bridge

The San Juan Creek Bridge Replacement Project is replacing the railroad bridge over San Juan Creek in the City of San Juan Capistrano.

The project is constructing a new three-span girder bridge west of the existing bridge. The new bridge will enhance safety, reduce maintenance needs, and meet current design and bridge load standards. The existing bridge will be demolished, and a new foundation and substructure will be installed for a potential future bridge. There are no plans to construct a second bridge but if a need arises, the supporting infrastructure will be in place.

The bridge serves Metrolink and Amtrak Pacific Surfliner passenger trains, as well as freight trains.

The project will also:

  •    Construct tracks
  •    Construct a new bikeway underpass
  •    Construct retaining walls
  •    Install new utilities and signals
  •    Remove vegetation

Construction Activities

Construction continues outside San Juan Creek as crews are working along the creek embankment. Current activities include concrete pours, equipment mobilization, and preparation for continued sheet pile installation.

Nighttime Equipment Relocation

Night work is scheduled to begin as early as 10 p.m. Friday, Oct. 9, to 5 a.m. Saturday, Oct. 10, to move construction equipment across the railroad tracks. This nighttime activity is necessary for the safe movement of equipment while minimizing impacts to passenger rail service.

Ongoing Sheet Pile Installation

Sheet pile installation along the top of the creek embankment is expected to continue intermittently through early 2027. Work hours are Monday through Friday, from 6 a.m. to 6 p.m.

Construction vehicles may continue to access the work area via Camino Capistrano and exit via Stonehill Drive. Water trucks will remain in use along the route to help minimize dust.

This work may be loud. The surrounding community may experience intermittently construction noise and vibration during sheet pile installation. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Latest Activity



Yellow alert within a circle
PDF
PDF
October 9, 2026
Yellow alert within a circle
PDF
PDF
October 2, 2026
Yellow alert within a circle
PDF
PDF
September 25, 2026
Yellow alert within a circle
PDF
PDF
September 18, 2026

Contact the Outreach Team

If you have any questions or would like to request information in another language, please contact the Outreach Team at (800) 724-0353 or email SJCBridge@octa.net.