San Juan Creek Trail Closure Update
What: The San Juan Creek Trail between Camino Capistrano and Trabuco Creek is expected to close during the workday for approximately two weeks. This closure would allow crews to safely stage equipment and materials, while placing rock slope protection along the embankment from outside the San Juan Creek.
The San Juan Creek Trail between Camino Capistrano and Trabuco Creek is expected to close during the workday for approximately two weeks. This closure would allow crews to safely stage equipment and materials, while placing rock slope protection along the embankment from outside the San Juan Creek.
When: The trail is expected to close as early as Thursday, Sept. 24, for approximately two weeks during construction, between 6:30 a.m. and 4:30 p.m., Monday through Friday. The trail is expected to reopen at the end of each workday and remain open on weekends.
The schedule is subject to change due to inclement weather or unforeseen operational issues.
San Juan Creek Trail Detour Map
Construction Activities
A project milestone was reached this week with the completion of construction activities within San Juan Creek. Crews have transitioned out of the creek and will continue working along the top of the embankment. Construction activities will include sheet pile cap work, rock slope protection, and sheet pile installation. The sheet pile installation is expected to continue intermittently through early 2027. Work hours are Monday through Friday, from 6 a.m. to 6 p.m. Construction equipment may continue to access the work area via Camino Capistrano and exit via Stonehill Drive. Water trucks will remain in use along the haul route to help minimize dust.
This work may be loud. The surrounding community may experience intermittently construction noise and vibration during sheet pile installation. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Sheet Pile Installation Location Map