Skip to main content

San Juan Creek Bridge Replacement Project

Construction Updates

The Orange County Transportation Authority (OCTA), in coordination with Metrolink, is replacing the railroad bridge over San Juan Creek. Built in 1917, the bridge has reached the end of its useful life and will be replaced by a new three-span girder bridge.

Project Details

SJC Bridge

The San Juan Creek Bridge Replacement Project will replace the railroad bridge over San Juan Creek in the City of San Juan Capistrano.

The project will construct a new three-span girder bridge west of the existing bridge. The new bridge will enhance safety, reduce maintenance needs, and meet current design and bridge load standards. The existing bridge will be demolished, and a new foundation and substructure will be installed for a potential future bridge. There are no plans to construct a second bridge but if a need arises, the supporting infrastructure will be in place.

The bridge serves Metrolink and Amtrak Pacific Surfliner passenger trains, as well as freight trains.

The project will also:

  •    Construct tracks
  •    Construct a new bikeway underpass
  •    Construct retaining walls
  •    Install new utilities and signals
  •    Remove vegetation

Construction Activities


In early September, a milestone was reached when the construction of four columns that are the foundational support for the new railroad bridge was completed. The creek was later restored to its original condition for the rainy season before crews return to the creek in Spring 2025 to continue building the railroad bridge.

creek

Bridge Abutments

Crews are focusing on constructing the new bridge abutments over the next several months, which include work such as drilling, installing piles and performing a series of concrete pours.


Retaining Wall

A new retaining wall within rail right of way next to the City Hall and Santa Margarita Water District facilities will be constructed to support the railroad track. The wall will be approximately 470' long and 6' tall.

Beginning the week of Oct. 21, crews are expected to pour concrete and drill piles during extended hours from 6 a.m. to 1 a.m. the following morning until the end of October. Construction vehicles will access the location using Paseo Adelanto.

Neighboring residents may experience noise from backup alarms and train horns, as well as lighting from nighttime operations.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

retaining wall

Community Impacts


San Juan Creek Trail

The San Juan Creek Trail is expected to close in mid-November for an extended period of time to allow crews to construct a retaining wall and perform work on the new railroad bridge. The closure will occur during work hours from 6 a.m. to 5 p.m. At the end of each shift, the trail will reopen to the public.

Train Horns

Federal Railroad Administration (FRA) guidelines require all trains to sound their horns when workers are present, in emergency situations or when there are trespassers on or around railroad tracks. This federal mandate applies to construction zones. As a result, for the safety of construction workers, train crews and passengers, and the public, horns will be sounded when trains pass through the area.

Additional Impacts

The public and businesses adjacent to the work area may experience noise and vibration from demolition and drilling activities as well as light from construction operations. Noise may also be generated from construction equipment back-up alarm. The alarms are required by state regulation.

Community Outreach

The Public Outreach team regularly hosts project information booths at Descanso Park in San Juan Capistrano and Doheny State Beach in Dana Point. In addition, the team participates in community events.

Businesses or civic organizations that would like to receive a project presentation may email the team at SJCBridge@octa.net.

We look forward to seeing you at:

Descanso Park
32506 Paseo Adelanto, San Juan Capistrano
Friday, Oct. 25 from 10 a.m. to 2 p.m.

Latest Activity

Document Icon
PDF
PDF
October 18, 2024
Document Icon
PDF
PDF
October 11, 2024
Document Icon
PDF
PDF
October 4, 2024
Document Icon
PDF
PDF
September 27, 2024
Document Icon
PDF
PDF
September 23, 2024
Document Icon
PDF
PDF
September 20, 2024
Document Icon
PDF
PDF
September 13, 2024
Document Icon
PDF
PDF
September 6, 2024
Document Icon
PDF
PDF
August 30, 2024
Document Icon
PDF
PDF
August 23, 2024
Document Icon
PDF
PDF
August 19, 2024
Document Icon
PDF
PDF
August 19, 2024
Document Icon
PDF
PDF
August 16, 2024
Document Icon
PDF
PDF
August 9, 2024
Document Icon
PDF
PDF
August 2, 2024
Document Icon
PDF
PDF
July 26, 2024
Blue pdf icon
pdf
pdf
July 15, 2024
Blue pdf icon
pdf
pdf
July 3, 2024
Blue pdf icon
pdf
pdf
June 28, 2024
Blue pdf icon
pdf
pdf
June 21, 2024
Blue pdf icon
pdf
pdf
June 14, 2024
Blue pdf icon
pdf
pdf
June 10, 2024
Blue pdf icon
pdf
pdf
May 31, 2024

Contact the Outreach Team

If you have any questions or would like to request information in another language, please contact the Outreach Team at (800) 724-0353 or email SJCBridge@octa.net.