FREEWAY
The Measure M freeway program includes 30 project segments that will relieve rush hour congestion and ease traffic flow on Orange County freeways. To date, 17 freeway segments have been completed and six more were under construction during 2025.
I-5 (SR-73 to El Toro Road) Improvement Project
From SR-73 to El Toro Road, OCTA and Caltrans completed the I-5 Improvement Project.
Located adjacent to the cities of Laguna Hills, Laguna Niguel, Lake Forest and Mission Viejo, the $699.4 million freeway improvement project was built in three segments and included numerous roadway, structural and operational improvements, as well as soundwalls. All freeway improvements on the three segments were opened to traffic in March 2025. Construction on the northerly segment (Alicia Parkway to El Toro Road) and the southerly segment (SR-73 to Oso Parkway which includes Avery Parkway Interchange) were completed in July 2025. A separate landscape contractor began plant establishment efforts for all three segments in June 2025, with completion anticipated in late 2026.
Learn more
I-5 (I-405 to SR-55) Improvement Project
OCTA and Caltrans are improving traffic operations by adding a general-purpose lane in each direction and enhancing safety on the on- and off-ramps and in merging areas of I-5 between I-405 and SR-55 in the cities of Irvine and Tustin. The $716 million freeway improvement project will be built in two segments. Construction of the northerly segment from Yale Avenue to SR-55 began in December 2025. The southerly segment from I-405 to Yale Avenue is anticipated to begin construction in early 2026.
Learn more
I-605 (Katella Avenue Interchange) Improvement Project
OCTA, in cooperation with Caltrans, is improving the local interchange at I-605 and Katella Avenue to improve mobility, smooth traffic flow, and enhance pedestrian and bicycle facilities. The $53 million project is funded with a combination of local and federal funds.
Construction is underway and the project is anticipated to be completed in 2027.
Learn more
SR-55 (I-405 to I-5) Improvement Project
OCTA and Caltrans are improving four miles of SR-55 between I-405 and I-5 through the cities of Irvine, Santa Ana, and Tustin. This project will improve traffic flow and reduce travel time by adding one regular lane and one carpool lane in each direction, making improvements to several bridges, and adding merge lanes between several interchanges. The $505.7 million project is funded with a combination of local, state, and federal funds.
Construction is underway and the project is anticipated to be completed in 2027.
Learn more
SR-57 (Northbound, Orangewood Avenue to Katella Avenue) Improvement Project
Located adjacent to the cities of Anaheim and Orange, this $135.4 million freeway improvement project will improve traffic flow and enhance freeway operation in the northbound direction on SR-57 from Orangewood Avenue to Katella Avenue. This project will add one northbound general-purpose lane, improve the northbound Katella Avenue off-ramp, and extend the merge length between the existing freeway on- and off-ramps to improve weaving distance. Construction began in October 2025.
Learn more
SR-91 (SR-57 to SR-55) Improvement Project
From SR-57 to SR-55, OCTA and Caltrans are working together to implement the SR-91 Improvement Project to improve mobility throughout the corridor, reduce weaving and merging between ramps, and improve on- and off-ramps sidewalks and bike lanes at Glassell Street, Tustin Avenue, and Lakeview Avenue interchanges.
Located adjacent to the cities of Anaheim, Fullerton, Orange, and Placentia, the $778.9 million freeway improvement project is being built in three segments.
Construction on segment 1 (SR-55 to Lakeview Ave) began in February 2025 and on segment 3 (Acacia Street to La Palma Avenue) in December 2025. Segment 2 (La Palma Avenue to SR-55) is anticipated to be advertised for construction in 2026.
Learn more
Next 10 Delivery Plan: 2025 Update
Since the approval of Measure M, the OCTA Board has continued to pursue the expeditious implementation of Measure M through the adoption of delivery plans. These comprehensive and balanced plans are developed to ensure that the promises made in the Measure M Transportation Investment Plan can continue to be delivered in concert with changes in economic conditions and revenue projections. To date, there have been three delivery plans: the Early Action Plan adopted in 2007, M2020 Plan adopted in 2012, and Next 10 Delivery Plan adopted in 2016. The Next 10 Delivery Plan was last updated in 2025 and spans fiscal year (FY) 2025-26 to 2034-35. It incorporated OCTA's strong revenue position and validated that Measure M can still be delivered consistent with commitments to the voters, though Metrolink’s long-term operating sustainability requires close monitoring and coordination. By 2030, 90 percent of the total number of freeway projects (27 out of 30) are anticipated to be delivered well in advance of 2041.
Learn more