SR-91 (SR-57 to SR-55) Improvement Project
Construction Updates
55-Hour Closure
WHAT
In preparation for the new interchange configuration, crews are anticipated to perform construction activities that will require a continuous 55-hour closure of the following:
WHEN
As early as 9 p.m., Friday, Feb. 27 to 4 a.m., Monday, March 2
CLOSURES
- Westbound SR-91 straight on-ramp at Lakeview Avenue
- One lane of southbound Lakeview Avenue
- One lane of northbound Lakeview Avenue
These closures are necessary to safely accommodate construction activities associated with the new interchange configuration.
Potential impacts may include backup alarms from construction vehicles, bright lights, noise, and traffic delays. This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.
Additional Sunday Night Full Closure
WHAT
Lakeview Avenue will be fully closed. Motorists will not have access to Lakeview Avenue. Refer to map to view provided detours below.
WHEN
6 p.m., Sunday, March 1 to 4 a.m., Monday, March 2
CLOSURES ON SUNDAY NIGHT:
- Both directions of Lakeview Avenue
- Two lanes of westbound SR-91 between westbound Lakeview off- and on-ramps
- Westbound SR-91 off-ramp at Lakeview
- Eastbound SR-91 on-ramp at Lakeview
- Westbound SR-91 straight on-ramp at Lakeview
- Westbound SR-91 loop on-ramp at Lakeview
Additionally, there will also be reduced lanes on the westbound SR-91 freeway from 8 p.m., Sunday, March 1 to 4 a.m., Monday, March 2.
Note: EB SR-91 off-ramp will remain open.
Closures and Detours
WHAT
Beginning at 4 a.m., Monday, March 2, motorists traveling both northbound and southbound on Lakeview Avenue will use a new signalized intersection to access the westbound SR-91 straight on-ramp as part of the new Lakeview configuration.
Beginning as early as 6 p.m., Sunday, March 1, the westbound SR-91 loop on-ramp at Lakeview Avenue will be permanently closed. Motorists are encouraged to follow posted detour signage and plan ahead.
This work may cause traffic delays. Drive carefully in the area.
WHEN
- New configuration in place: 4 a.m., Monday, March 2
- Permanent closure of westbound SR-91 loop on-ramp: As early as 6 p.m., Sunday, March 1
CLOSURES
- Westbound SR-91 loop on-ramp at Lakeview Avenue (permanent closure)
As of July 7, 2025, Eastbound SR-91 Loop On-Ramp is Closed for Approximately Two Years

Construction on Segment 2 of the SR-91 Improvement Project is expected to begin in mid-2026.
Segment 3 Construction Coming Soon
Construction on Segment 3 of the SR-91 Improvement Project is expected to begin in early 2026, bringing major upgrades to the SR-91/SR-57 interchange and surrounding areas to improve traffic flow, enhance safety, and support long-term mobility.
Closures and Detours

A key element of this work is the full reconstruction of the La Palma Avenue bridge, which will provide modern lanes, wider sidewalks, and improved shoulders for drivers, pedestrians, and cyclists. To complete this effort, the existing bridge will first be demolished during two weekends of 55-hour directional closures on SR-91, followed by a year-long closure of the bridge itself to allow for reconstruction.
Stay informed with updates
Sign up for our construction alerts, which will be sent regularly when construction starts, by filling out the Stay Informed form. If you have further questions, please feel free to contact our team and we will be happy to help. Previous weekly construction alerts are posted at the bottom of this page.
NEW! You can now sign up to receive important construction notifications. Text SR91PROJECT to 877-676-4182 to subscribe.
Construction Closures & Detours
Closures and detours for the SR-91 Improvement Project
Social Media Feed
Latest Activity
- As of Jan. 5, 2026
- As of Dec. 22, 2025
- As of Dec. 12, 2025
- As of Dec. 5, 2025
- As of Nov. 21, 2025
- As of Nov. 14, 2025
- As of Nov. 3, 2025
- As of Oct. 31, 2025
- As of Oct. 24, 2025
- As of Oct. 17, 2025
- As of Oct. 13, 2025
- As of Oct. 3, 2025
- As of Sep. 29, 2025
- As of Sep. 22, 2025
- As of Sep. 15, 2025
- As of Sep. 8, 2025
- As of Aug. 29, 2025
- As of Aug. 22, 2025
- As of Aug. 15, 2025
- As of Aug. 8, 2025
- As of August 4, 2025
- As of July 25, 2025
- As of July 18, 2025
- As of July 11, 2025
- As of July 3, 2025
- As of June 27, 2025
- As of June 20, 2025
- As of June 13, 2025
- As of June 6, 2025
- Week May 30, 2025
- Week May 23, 2025
- Week May 16, 2025
- Week of May 9, 2025
- Week of May 2, 2025
- Week of April 25, 2025
- Week of April 21, 2025
- Week of April 14, 2025