November 12, 2024
The Orange County Transportation Authority’s board received a progress report on the 2024 Board of Directors and CEO Initiatives and Action Plan that guides the agency’s efforts throughout the year.
The action plan consists of three board initiatives supported by nine CEO initiatives that are monitored through 107 milestones throughout the year.
Twenty milestones were completed between July 1 and Sept. 30. Those include:
- Awarding a construction contract for OCTA’s Transit Security and Operations Center.
- Allocating more than $42 million in Measure M funding to support 13 local transit projects.
- Approving the purchase of a new property for OCTA's future administrative headquarters.
- Working collaboratively with external agencies to update the initial conceptual solutions in the Coastal Rail Resiliency Study.
- Progressing on the environmental phase of the OC Connect project, which would create a biking and walking trail in the cities of Garden Grove and Santa Ana.
The OCTA board received an update on how the agency is actively working to improve safety and support walking and biking throughout Orange County.
OCTA began working on its E-bike Safety Action Plan in summer 2023 due to the growing use of e-bikes throughout the county. The plan includes strategies for improving infrastructure, education and legislation to promote the safe use of e-bikes. The final plan is expected to be available by the end of 2024. More information is available at octa.net/ebikes.
In addition, OCTA has been working with the Orange County Health Care Agency on a Safe Routes to School Program to encourage safe walking and biking to school. These efforts include the Next STEP program, which partners with cities and local police departments to promote walking and bicycling education and evaluating infrastructure needs at 25 eligible public elementary schools across Orange County. For more, visit octa.net/SafeRoutestoSchool.
OCTA is also continuing work on the environmental process of the OC Connect project that would create a 4-mile shared-use path in Garden Grove and Santa Ana. The environmental process is expected to be completed by June 2025. To learn more, visit octa.net/OCConnect.
The OCTA board approved the 2024 Measure M Next 10 Delivery Plan, which outlines how OCTA will deliver $5.6 billion in transportation improvements over the next decade as promised to Orange County voters through Measure M.
The updated Next 10 Plan incorporates this year’s Measure M forecast. The half-cent sales tax for transportation improvements is expected to generate $14 billion through 2041.
Highlights from the Next 10 Plan include:
- Completing approximately 90% of the freeway projects included in the Measure M plan by 2030, 10 years ahead of schedule.
- Continuing to fund the preservation of OCTA’s open space properties that were purchased through the Environmental Mitigation Program.
- Continuing to support the coordination of traffic signals across more than 2,000 intersections in Orange County to improve traffic flow and reduce congestion.
- Continuing to provide funding to cities and the county for local transportation needs through the Local Fair Share Program, as well as ongoing grants to improve streets through the Regional Capacity Program.
- Completing construction and beginning operations of the OC Streetcar.
- Continuing to provide funding for local transit services, including shuttles and trolleys, as well as offering enhanced mobility options for seniors and people with disabilities.
- Providing ongoing grants to improve water quality throughout Orange County through the Environmental Cleanup Program.
To access the full plan, visit octa.net/Next10.
Board Actions Archive
November 12, 2024
Overview- OCTA Receives Updates on Board and CEO Action Plan
- OCTA Continuing to Make Biking, Walking Easier in Orange County
- Board Approves 2024 Next 10 Delivery Plan
October 28, 2024
Overview- October Employees of the Month Recognized
- OCTA Reaching a Diverse Orange County through Outreach Efforts
- OC Streetcar Construction Nearly 90% Complete
October 14, 2024
Overview- OCTA Board Approves Nearly $11 Million to Improve O.C. Water Quality
- OCTA Begins Development of 405 Express Lanes Expenditure Plan
- Measure M 10-Year Review Underway
September 23, 2024
Overview- September Employees of the Month
- Board Receives Service Change Update
- OCTA Board Accepts Programming Recommendations for Project V
September 9, 2024
Overview- August Employees of the Month
- Board Receives Traffic Signal Synchronization Program Update
- OCTA Board Accepts Grants to Advance Sustainability Efforts
August 12, 2024
Overview- Board Makes More than $40 Million Available to Help Ease Congestion in O.C.
- Board Receives Update on South County Improvements
- I-5 South County Improvements Nearing Finish Line
July 22, 2024
Overview- Board Honors July Employees of the Month
- OC Streetcar Construction 86% Complete
July 8, 2024
Overview- OCTA Board Receives Measure M 10-Year Comprehensive Review Survey Results
- Board Receives Mid-Year Update on 2024 Initiatives
- OCTA Continues Efforts to Improve Biking, Walking in O.C.
June 24, 2024
Overview- OCTA Approves 2024-25 Fiscal Year Budget
- Board Honors June Employees of the Month
- Board Names New Taxpayer Oversight Committee Members, Recognizes Teen Council
June 10, 2024
Overview- OCTA Continues Delivering on Measure M Promises
- Board Takes Next Step Toward Safer Routes to Schools
May 28, 2024
Overview- Board Honors May Employees of the Month
- Board Receives Update on Study Aimed at Improving O.C.'s Transit Future
May 13, 2024
Overview- Board Receives Update on Coastal Rail Resiliency Efforts
- Budget Workshop Held to Discuss Proposed FY 2024-25 Budget
April 22, 2024
Overview- Board Honors April Employees of the Month
- OCTA Board Seeks Firm to Provide Video Streaming Services
- Board Approves Purchase of Driver Barriers
April 9, 2024
Overview- OCTA Maintains Strong Financial Health Despite Sales Tax Decline
- Board Discusses 2028 Olympic Transportation Plans
March 25, 2024
Overview- Board Honors March Employees of the Month
- OCTA Takes Step Toward a Zero-Emission Future
- Minor Updates Coming to OC Bus Schedule in May
March 11, 2024
Overview- OCTA Contributes $27.5 Million to Preserve Habitat and Wildlife
- I-5 South County Improvements Nearing Finish Line
- OCTA Continues Work to Protect Coastal Rail Line
February 26, 2024
Overview- Board Honors February Employees of the Month
February 12, 2024
Overview- OCTA Sets 2024 Standards with CEO and Board Initiatives
- $18.5 Million Available to Improve Orange County Water Quality
- OCTA en Route to a Zero-Emission Future
January 22, 2024
Overview- Board Honors January Employees of the Month
- Board Members Appointed to External Agencies
January 8, 2024
Overview- OCTA Board Selects Tam T. Nguyen to Serve as Chair
- Board Reflects on 2023 Accomplishments
December 11, 2023
Overview- OCTA Recognizes Outgoing Board Members
- Board Honors December Employees of the Month
- OCTA Continues to Deliver on Measure M Projects
November 27, 2023
Overview- Board Honors November Employees of the Month
- OCTA Continues Enhancing Bus Operations Planning
- I-405 Improvement Project to Open Dec. 1
November 13, 2023
Overview- OCTA Receives Update on Board and CEO Action Plan
- Cities Invited to Apply for Community Shuttle Services
- Board Approves 2023 Next 10 Delivery Plan
October 23, 2023
Overview- Board Honors October Employees of the Month
- Quicker Commute Coming Dec. 1 With Opening of I-405 Improvements
- Board Advances Orange County Maintenance Facility
October 9, 2023
Overview- Measure M Expected to Generate $14.8 Billion Through 2041
- Board Receives Forecast of Construction Market Conditions
- Board Approves Nine State Project Program Recommendations
September 25, 2023
Overview- OCTA Reappoints Public Board Member Hennessey
- Board Honors September Employees of the Month
- OCTA Board Accepts $42 million Grant for SR-91 Improvements
- OCTA Board Approves Request for Proposals for SR-91 Project
August 28, 2023
Overview- Board Honors August Employees of the Month
- OCTA Board Advances I-405 Outreach Plans
August 14, 2023
Overview- Board Approves $3.4 Million to Help Protect Orange County’s Water Quality
- OCTA Issues Call for Projects to Improve Mobility in Orange County
- OCTA Selects Consultant for Coastal Rail Study
July 24, 2023
Overview- Board Recognizes July Employees of the Month
- OCTA Board Approves 405 Express Lanes Toll Policy
July 10, 2023
Overview- Board Reviews 2023 Strategic Initiatives Mid-Year Report
- OCTA Makes Progress on SR-55 Improvement Project
- Board Approves Collaboration with Caltrans on SR-91 Improvements
June 26, 2023
Overview- Board Recognizes June Employees of the Month
- OCTA Board Appoints Public Committee Members
June 12, 2023
Overview- OCTA Approves 2023-24 Fiscal Year Budget
- Board Declares Emergency Resolution for San Clemente Tracks
- I-405 Improvement Project Now 95% Complete
May 22, 2023
Overview- Board Recognizes May Employees of the Month
- Board Receives Update on I-5 South County Improvements
May 8, 2023
Overview- Board Receives Update on 2023 Initiatives
- Board Approves Final Long-Range Transportation Plan
- Workshop Held to Discuss Proposed FY 2023-24 Budget
April 24, 2023
Overview- Board Recognizes April Employees of the Month
- OCTA Selects Outreach Firm for I-5/El Toro Road Interchange Project
- Board Approves Updated Funding Plan for I-405 Improvement Project
April 10, 2023
Overview- Passenger Rail Service between Orange and San Diego Counties to Resume April 17
- Board Honors Employee Rotation Program Graduates
- OCTA Board Awards $37 Million to Improve Orange County Streets
March 27, 2023
Overview- Board Recognizes March Employees of the Month
- OCTA Board Advances 405 Express Lanes
- OCTA Selects Outreach Firm for SR-91 Improvement Project
March 13, 2023
Overview- Board Receives 91 Express Lanes Update
- OCTA Begins Procurement Process for South Coast Rail Study
- Board Selects Firms for Freeway Services Patrol Services
February 27, 2023
Overview- OCTA Board Honors 2022 Employees of the Year
- Board Recognizes February Employees of the Month
- Board Approves Framework for Finding Coastal Rail Solutions
February 13, 2023
Overview- OCTA Saves Taxpayers $509 Million through Innovative Financing
- $3 Million Available to Protect County’s Oceans and Waterways
- Board Receives Update on Long-Range Transportation Plan
January 23, 2023
Overview- Board Recognizes January Employees of the Month
- Board Sets Transportation Vision for 2023
- OC Streetcar Construction 78% Complete
January 9, 2023
Overview- OCTA Appoints New and Returning Board Members
- Board Reviews 2022 Initiatives and Action Plan
- OCTA’s Zero-Emission Bus Pilots Creating a Cleaner O.C.
December 12, 2022
Overview- OCTA Board Approves Maintenance Employee Contract
- Board Commemorates Outgoing Members
- Board Recognizes December Employees of the Month
November 28, 2022
Overview- OCTA Honors Outgoing Board Members
- Board Recognizes November Employees of the Month
- Board Receives Employment and Travel Follow-up Survey Results
November 14, 2022
Overview- OCTA Awards $3.1 Million to Improve Water Quality
- Board Approves Strategies to Improve South O.C. Transportation
- OCTA Continues Delivering on Promises with Updated Next 10 Plan
October 24, 2022
Overview- Board Recognizes October Employees of the Month
- OC Streetcar Construction 73% Complete
- Board Approves Making Better Connections Plan
October 10, 2022
Overview- Measure M Contributes $1 Billion to Orange County Streets
- Board Receives Update on 2022 Long-Range Transportation Plan
- Board Receives Report on Construction Market Conditions
September 26, 2022
Overview- Board Recognizes September Employees of the Month
- Measure M Expected to Generate $15 Billion Through 2041
September 12, 2022
Overview- Adjustments to Bus Schedule Go into Effect Oct. 9
- Board Approves Updated 2023 Active Transportation Program Regional Project Points
August 22, 2022
Overview- Board Recognizes August Employees of the Month
- OCTA Approves SB 1 Program Recommendations for Fiscal Year 2022-23
August 8, 2022
Overview- OCTA’s Student Bus Pass Program Expands to All O.C. Community Colleges
- Board Issues $45 Million Call for Projects to Help Ease Congestion in Orange County
- I-405 Improvement Project Now 80% Complete
July 25, 2022
Overview- OCTA Receives Public Feedback on Draft Bus Restructuring Plan
- Board Recognizes July Employees of the Month
July 11, 2022
Overview- OCTA Makes Progress on 2022 Initiatives and Action Plan
- New Members Selected for Taxpayer Oversight Committee
- OCTA Planning for O.C.’s Transportation Future
June 27, 2022
Overview- OCTA Continues to Fulfill Promises to Voters through Measure M
- Board Recognizes June Employees of the Month
- Board Receives Update on South County Transportation Study
June 13, 2022
Overview- OCTA Approves $1.65 Billion Balanced Budget for FY 2022-23
- Measure M Continuing to Improve Orange County Mobility
May 23, 2022
Overview- Board Approves Draft Plan Aimed at Improving Bus Service
- Board Recognizes May Employees of the Month
- Minor Service Changes Coming to OC Bus June 12
May 9, 2022
Overview- OCTA Awards $26.4 Million to Improve Orange County Streets
- Board Receives CEO Initiatives and Action Plan Progress Report
- Workshop Held to Discuss Proposed FY 2022-23 Budget
April 25, 2022
Overview- Board Selects Consultant for South Orange County Rail Station Feasibility Study
- OCTA Selects Community Outreach Consultant for OC Streetcar Project
- Board Recognizes April Employees of the Month
April 11, 2022
Overview- OCTA Board Calls for Bids for SR-55 Improvements
- OCTA Continues to Mitigate Impacts from OC Streetcar Construction
March 28, 2022
Overview- I-5 South County Improvements Project Progresses
- Board Recognizes March Employees of the Month
- Environmental Work on I-5 Carpool Extension Continues
March 14, 2022
Overview- $3 Million Available to Protect Orange County Beaches and Waterways
- Board Receives Update on Efforts to Synchronize Traffic Signals
- Measure M Continues to Deliver Projects and Programs that Keep Orange County Moving
February 28, 2022
Overview- Board Recognizes February Employees of the Month
- Traffic Volumes on 91 Express Lanes Exceed Pre-Pandemic Levels
February 14, 2022
Overview- OCTA Continues Youth Ride Free Pass Beyond Promotional Period
- SR-55 Improvement Project Advances with Consultant Selection
- OCTA Honors Outstanding Employees of the Year
January 24, 2022
Overview- Board Recognizes January Employees of the Month
- OCTA Launches Making Better Connections Study
- Initiatives for 2022 Focus on Equity, Transparency, Fiscal and Environmental Responsibility
January 10, 2022
Overview- OCTA Board Selects Chairman and Vice Chairman for 2022
- OCTA Keeps Orange County Moving in 2021 with Focus on Safety and Sustainability
- Board Reviews 2021 Board and CEO Initiatives and Action Plan
December 13, 2021
Overview- Board Recognizes December Employees of the Month
- Board Receives Update on Zero-Emission Bus Pilot Program
- Board Receives Employment and Travel Survey Results
- OCTA Continues Delivering on Promises with Updated Next 10 Plan
November 22, 2021
Overview- Board Recognizes November Employees of the Month
- OCTA Awards Nearly $3 Million to Improve Transportation for Seniors and People with Disabilities
- Board Receives Attitudinal and Awareness Survey Results
November 8, 2021
Overview- Board Receives Update on Efforts to Synchronize Traffic Signals
- I-405 Improvement Project Construction Progresses
- Board Receives Quarterly Progress Report on CEO Action Plan
October 25, 2021
Overview- Board Recognizes October Employees of the Month
- Improvements Rolling Along at Anaheim Canyon Metrolink Station
- OC Streetcar Construction Progresses
October 11, 2021
Overview- OCTA Collaborates with Caltrans on I-605/Katella Avenue Project
- OCTA Seeks Firm to Implement OC Streetcar Ticket Vending Machines
September 27, 2021
Overview- Measure M Expected to Generate $13.2 Billion Through 2041
- SR-55 Improvement Project Progresses
- Board Recognizes September Employees of the Month
September 13, 2021
Overview- Board Receives Update on South County Transportation Study
- OCTA to Provide Additional Bus Service Next Month
- OCTA Using Creative Financing to Save $20 Million on 405 Project
August 23, 2021
Overview- Board Recognizes August Employees of the Month
- OCTA Approves SB 1 Program Recommendations
- I-405 Improvement Project Now More than 60% Complete
August 9, 2021
Overview- Board Issues $40 Million Call for Projects to Help Ease Traffic in Orange County
- OCTA Invests $2.7 Million to Clean Orange County Water
- OCTA Board Awards Contract for 405 Express Lanes Back-Office
July 26, 2021
Overview- Board Recognizes July Employees of the Month
- Board of Directors Receives State Legislative Status Report
- Board of Directors Receives Federal Legislative Status Report
July 12, 2021
Overview- Northbound SR-57 Improvements Advance with Consultant Selection
- Board Takes Step Toward Free Bus Rides for Youth
- Board Receives Strategic Initiatives Mid-Year Report
June 28, 2021
Overview- Board Recognizes June Employees of the Month
- Taxpayer Oversight Committee Gains New Members
- OCTA Fulfilling Measure M Promises for 30 Years Straight
June 14, 2021
Overview- OCTA Approves $1.3 Billion Balanced Budget for FY 21-22
- OCTA Releases the Draft 2021 SR-91 Implementation Plan
- Board Approves Bus Service Change for June 13
- Board Receives Update on Regional Traffic Signal Synchronization Program
May 24, 2021
Overview- Board Recognizes May Employees of the Month
- OCTA Allocates Low Carbon Transit Operations Program Funds
- Board Approves Bus Service Change for June 13
- OCTA Board Participates in Future of Transit Workshop
May 10, 2021
Overview- OCTA Awards $28.7 Million to Improve Orange County Streets
- Board Receives Update on South County Improvements
- Workshop Held to Discuss Proposed FY 2021-22 Budget
April 26, 2021
Overview- Board Recognizes April Employees of the Month
- Public Hearing Held for Upcoming Bus Service Change
- Board Approves Comprehensive Business Plan
April 12, 2021
Overview- OCTA Board Welcomes New Members
- OCTA Continues to Deliver with Updated 10-year Measure M Plan
- OCTA Selects Firm to Aid in OC Bus Restructuring
- OCTA Advances SR-55 Improvement Project with Consultant Selection
March 22, 2021
Overview- March Employees of the Month Recognized
- Construction Contract Awarded for Anaheim Canyon Metrolink Station Improvements
- Board Calls for Bids for Battery-Electric Bus Chargers
March 8, 2021
Overview- OCTA Setting Vision for Mobility Hubs in O.C.
- Northbound SR-57 Project Advances
- Board Receives Update on I-5 Improvements in South County
February 22, 2021
Overview- February Employees of the Month Recognized
- Board Receives Update on 91 Express Lanes
- OCTA Requests Feedback from the Public on Bus Service Changes
February 8, 2021
Overview- 2020 Employees of the Year Honored
- $2.8 Million Available to Improve County’s Water Quality
- OCTA Developing Strategies to Improve Travel in South Orange County
January 25, 2021
Overview- January Employees of the Month Recognized
- Board Sets Transportation Vision for 2021
- OCTA Purchases Charging Stations for Light-Duty Vehicles
- Community Transit Program Requirements Revised Due to Pandemic
January 11, 2021
Overview- OCTA Board Elects Do as Chairman, Murphy as Vice Chair
- OCTA Swears in New and Returning Board Members
- SR-55 Project Receives $140 million from CTC
December 14, 2020
Overview- OCTA Bids Farewell to Outgoing Board Members
- I-5 Widening Project Progresses
- I-405 Improvement Project Update
November 23, 2020
Overview- OCTA Bids Farewell to Outgoing Board Members
- OC Flex Pilot in South O.C. Extended Through 2021
- OCTA Continuing to Proactively Respond to COVID-19
November 9, 2020
Overview- Signal Synchronization Coming to Warner Avenue
- OCTA Purchases Battery-Electric Buses
- Board Receives Strategic Initiatives Quarterly Update
October 26, 2020
Overview- SR-55 Improvement Project Progresses
- OCTA Signal Synchronization Program Saves Time, Money, Helps the Environment
- Measure M Expected to Generate $11.6 Billion Through 2041
October 12, 2020
Overview- OCTA Awards $2.8 Million to Improve O.C.’s Water Quality
- I-5 Project in South Orange County Advances
- OCTA Studying Development Opportunities for Fullerton Park-and-Ride
September 28, 2020
Overview- SCAG Sheds Light on Pandemic’s Impact to Regional Travel
- Board Receives Update on Hydrogen Fuel-Cell Bus Performance
- Survey Demonstrates how COVID-19 has Affected Employment, Travel
September 14, 2020
Overview- Board Receives Update on OC Go Progress
- Upgrades Headed to Busy Bus Stops in Santa Ana
- Survey Demonstrates how COVID-19 has Affected Employment, Travel
August 24, 2020
Overview- OC Go to Fund Senior Mobility Program in Laguna Beach
- Board Requesting Proposals for Maintenance of Environmental Properties
- Measure M Forecast Declines due to COVID-19 Impacts
August 10, 2020
Overview- OCTA Board Commends Essential Workers, Pilots Distribution of Free Face Coverings
- OCTA Adds All-Electric Support Vehicles to Fleet
- Board Receives Updates on South County Improvements
July 27, 2020
Overview- OCTA Proactively Responding to COVID-19
- Board Receives Update on Annual Rating Agency Meetings
- OCTA Board Awards Contract for OC Bus Communications
July 13, 2020
Overview- OCTA Board Pays Tribute to Director Winterbottom
- SR-91 Plan Details $1.3 Billion of Planned Improvements
- OCTA Meeting Major Transportation Milestones Despite Pandemic Challenges
June 22, 2020
Overview- OCTA Continues to Fulfill Measure M Promises to Voters
- Board Approves Plan to Transition to All Zero-Emission Buses
- I-5 Project in South Orange County Advances
June 8, 2020
Overview- OCTA Board Approves $1.4 Billion Budget
- OCTA Proactively Responding to COVID-19
- Board Receives Update on Measure M Progress
May 22, 2020
Overview- Board Awards Contract to Operate and Maintain OC Streetcar
- Service Changes Coming to OC Bus on June 14
- Construction Progresses on I-405 Improvements
May 11, 2020
Overview- Board Receives COVID-19 Update
- SR-55 Improvements Expected to Break Ground Next Year
- Workshop Held to Discuss Proposed FY 2020-21 Budget
April 27, 2020
Overview- Board Receives COVID-19 Update
- OCTA to Add Plug-in Electric Buses to Fleet
- Solutions Developed to Improve Beach Boulevard Travel
April 13, 2020
Overview- Board Receives COVID-19 Update
- Three Projects Advancing to Address South County Traffic
- $9.2 Million Awarded to Local Transit
March 23, 2020
Overview- Board Receives COVID-19 Update
- OCTA to Purchase 299 Replacement Buses
- OC Streetcar Construction Progressing
March 9, 2020
Overview- Deputy CEO Recognized for Service at OCTA
- $2.8 Million Available to Improve O.C. Water Quality
- Board Receives I-5/El Toro Road Interchange Update
February 24, 2020
Overview- February Employees of the Month Recognized
- OCTA to Roll Out Zero-Emission Buses
- OCTA Working with Local Businesses During OC Streetcar Construction
February 10, 2020
Overview- 2019 Employees of the Year Honored
- Rotation Program Participants Recognized
- Measure M Signal Synchronization Keeping O.C. Moving
January 27, 2020
Overview- January Employees of the Month Recognized
- Board Sets Transportation Vision for 2020
- Board Extends OC Flex Pilot Through October
January 13, 2020
Overview- Steve Jones Selected as New OCTA Chairman
- OCTA Board Looks Back at Last Year’s Accomplishments
- Board Reviews February Bus Service Changes
- I-405 Improvements Continue into 2020
December 9, 2019
Overview- December Employees of the Month Recognized
- Director Moreno Honored for Service to OCTAs
- Local Sales Tax Funds Working to Preserve the Environment
- Options Explored for Future Express Lanes
November 25, 2019
Overview- November Employees of the Month Recognized
- 91 Express Lanes Usage Exceeds Expectations
- OC Streetcar Construction Rolling Along
November 11, 2019
Overview- Next 10 Plan Bringing Balanced Transportation Improvements to O.C.
- Board Receives CEO’s Third Quarter Initiatives Update
- Board Recognizes Management Development Academy Graduates
October 28, 2019
Overview- October Employees of the Month Recognized
- Measure M Expected to Bring in $13.4 Billion
- Agreement Reached for 241/91 Tolled Connector
October 14, 2019
Overview- OC Bus 360° Keeps Orange County Moving
- Board Receives Metrolink Performance Report
- Cities Invited to Apply for Community Shuttle Services
September 23, 2019
Overview- September Employees of the Month Recognized
- Bus Service Changes set for October
- SR-91 Improvement Project Advances
- Board Sets Plan for Using State Transportation Funds
September 9, 2019
Overview- August Employees of the Month Recognized
- OCTA Board Awards $2 Million to Improve Water Quality
- OCTA Awarded $100,000 Safety Grant
- 405 Improvements Progress Through 2019
August 12, 2019
Overview- Measure M Working to Preserve the Environment
- $40M OK’d to Help Ease Traffic Through Measure M
- Local Transit Projects Meeting Community Needs
July 22, 2019
Overview- July Employees of the Month Honored
- Summer College Interns Recognized
- Bus Service Changes to go into Effect in October, February
- OC Streetcar Construction Moving Along
July 8, 2019
Overview- OCTA Honors Bus Roadeo Team
- New Members Selected for Taxpayer Oversight Committee
- Board Reviews Strategic Initiatives Progress
- Board Receives CEO’s Second Quarter Initiatives Update
June 24, 2019
Overview- June Employees of the Month Honored
- Board Recognizes Teen Council for Year of Service
- OCTA Fulfilling Promises to Voters Through Measure M
June 10, 2019
Overview- OCTA Board Approves $1.5 Billion Balanced Budget
- Public Provides Feedback on Proposed Bus Service Changes
- Board Approves $20.4 Million to Improve Biking, Walking in O.C.
- $8.5 Million Awarded to Help Ease Traffic Through OC Go
May 24, 2019
Overview- May Employees of the Month Recognized
- OC Flex Celebrates Six Months of Service
- I-5 South County Improvements to Break Ground
May 13, 2019
Overview- Workshop Held to Discuss Proposed FY 2019-20 Budget
- Board Approves June Bus Service Changes
- SR-91 Improvement Project Advances
April 22, 2019
Overview- OCTA Welcomes Board Member Don Wagner
- April Employees of the Month Recognized
- OC Bus 360° Continues Innovating to Meet Community Needs
- Study to Evaluate Transit Improvements on Bristol Street
April 8, 2019
Overview- Program Shuttles 1.8 Million People
- New App Keeps 405 Project Info at Commuters' Fingertips
- I-5 Freeway Construction in Central O.C. Gets Going
March 25, 2019
Overview- March Employees of the Month Recognized
- OC Streetcar Construction to Ramp Up in 2019
- Vanpool Program Saves Commuters Money, Time
March 11, 2019
Overview- Board Receives Measure M Quarterly Progress Report
- OCTA Looking to Clean Up Transportation-Related Pollution
- OCTA Delivering on Promises to Taxpayers
February 25, 2019
Overview- February Employees of the Month Recognized
- Board Receives Update on Sale of Measure M Bonds
- OCTA Testing Zero-Emission Technology
February 11, 2019
Overview- Employees of the Year Recognized
- 2019 CEO Initiatives and Action Plan Presented
- Caltrans Provides Updates on SR-22 Improvements
January 28, 2019
Overview- January Employees of the Month Recognized
- Chairman Shaw Announces 2019 Board Strategic Initiatives
- Board Approves Issuing Bonds for I-405 Improvement Project
January 14, 2019
Overview- Tim Shaw Selected as New OCTA Chairman
- Board Looks Back to OCTA's Accomplishments in 2018
- 405 Improvements Continue into 2019
December 10, 2018
Overview- December Employees of the Month Honored
- OCTA Welcomes Three New Board Members
- OC Active Sets Countywide Active Transportation Priorities
- Board Receives CEO’s Third Quarter Initiatives Update
November 26, 2018
Overview- November Employees of the Month Honored
- Outgoing Board Members Honored for Service to OCTA
- OC Bus 360° Keeping Orange County Moving
November 11, 2018
Overview- Hasan Ikhrata Recognized for Contributions to Orange County
- Long-Range Transportation Plan Sets Vision for Future of Transportation
- OC Streetcar Rolls Ahead with Approved Vehicle Design
October 22, 2018
Overview- October Employees of the Month Honored
- OCTA Working to Improve County’s Busiest Bus Stops
- Board Receives Report on Potential Prop. 6 Impacts
October 8, 2018
Overview- Grant Awarded to Improve Pedestrian and Bicycle Safety
- Significant Progress Achieved on Measure M2 Projects from April to June
- Interstate 5/El Toro Road Interchange Project Moves Ahead
September 24, 2018
Overview- OCTA Awards $220.5 million OC Streetcar Construction Contract
- OCTA Offering $25 million for Bikeway Projects
- September Employees of the Month Honored
September 10, 2018
Overview- $2.5 Million Awarded to Improve Orange County's Water Quality
- Next 10 Plan Updated to Keep Promises to Voters
- I-405 Construction Ongoing to Speed up Commutes
- Board Receives Update on SR-57 Northbound Improvement Project
August 27, 2018
Overview- July Employees of the Month Honored
- OC Streetcar Vehicle Designs OK'd for Public Input
- Awareness of OCTA at an All-Time High
- Early Career Academy Participants Recognized
August 13, 2018
Overview- Draft Long-Range Transportation Plan to be Released for Public Comment
- $40 million OK'd to Help Ease Traffic Through OC Go
- OC Flex Microtransit Program Expected to Launch this Fall
July 23, 2018
Overview- July Employees of the Month Honored
- Bristol Street Transit Corridor Study to Begin
- Planned Anaheim Canyon Metrolink Station Improvements Advance
- OC Go Revenue Forecast Dips
July 9, 2018
Overview- New 91 Express Lanes Account Plans Bring Simplicity, Cost Savings to Customers
- Board Approves Updated OC Streetcar Project Funding Plan
June 25, 2018
Overview- June Employees of the Month Honored
- Central Harbor Boulevard Transit Study Wraps Upn
- $6.8 Million Headed to Improve Local Transit
June 11, 2018
Overview- Board Approves $1.3 Billion Balanced Budget
- Measure M2 Quarterly Progress Report Given
- Comprehensive Transportation Funding Programs Approved
- New Members Chosen for Taxpayer Oversight Committee
- Citizens Advisory Committee members selected
May 25, 2018
Overview- May Employees of the Month Honored
- 2018 OCTA Roadeo Team Recognized
- 91 Express Lanes Usage Grows with Expansion in Riverside County
- First Quarter Progress Report Presented
May 14, 2018
Overview- Workshop Held to Discuss Proposed Fiscal Year 2018-19 Budget
- June Bus Service Changes
- Beach Boulevard Study Rolls Forward
April 23, 2018
Overview- April Employees of the Month Honored
- OCTA Expands Bicycle Capacity on Bus Fleet
- OC Bus 360° Continues Delivering to Meet Community Needs
April 9, 2018
Overview- OCTA Continues to Plan for the Future of Transportation
- OCTA Update on I-405 Improvement Project
- OCTA Awards Contract for Manufacturing and Delivery of Streetcars
March 26, 2018
Overview- March Employees of the Month Honored
- Firm Selected to Provide OC Flex Pilot Program
- OCTA Awards Contract for Manufacturing and Delivery of Streetcars
March 12, 2018
Overview- OCTA Commemorates 15 Years of the 91 Express Lanes
- OCTA Looking to Clean Up Transportation-related Pollution
- Caltrans Plans Eastbound SR-22 Safety Improvement Project
February 26, 2018
Overview- February Employees of the Month Honored
- 2018 CEO Initiatives and Action Plan Presented
- Toll Lanes System Integrator Contractor Selected
February 12, 2018
Overview- Employees of the Year Honored
- Transit Master Plan Sets Vision for Future of Transit
- Development of 2018 Long-Range Transportation Plan Continues
January 22, 2018
Overview- January Employees of the Month Honored
- 2017 Year in Review
- 2018 Board Strategic Initiatives Announced
- CEO Provides End-of-Year Action Plan Update
January 8, 2018
Overview- OCTA Selects New Board Chair and Vice Chair
- 2017 Year in Review
- Local Transit Projects Look to Meet Community Needs
- Central Harbor Boulevard Transit Study Rolls Forward
December 11, 2017
Overview- December Employees of the Month Honored
- Quarterly Report Given on Measure M2 Projects
- Interstate 405 Improvement Project Continues Moving Forward
- OCTA Board Requests TCA Defer 241/91 Express Lanes Toll Connector Project
November 13, 2017
Overview- OC Bus 360° Continues to Work to Reverse Declining Ridership
- Transit Master Plan is Mapping Future Transit in O.C.
- OCTA to Purchase 10 Hydrogen Fuel Cell Electric Buses
- Next 10 Delivery Plan Looks at What’s Ahead for Measure M2
October 23, 2017
Overview- October Employees of the Month Honored
- OC Flex Pilot Program Gets Green Light
- Board OKs Revised Bus Service Changes Based on Public Input
- Metrolink Fiscal Year 2016-17 Performance Report Presented
October 9, 2017
Overview- Long-Range Transportation Plan Moves Forward with Proposed Scenarios
- SB 1 Competitive Programs
- OC Congestion Management Program Report Released for Public Review
September 25, 2017
Overview- September Employees of the Month Honored
- Public Weighs in on Proposed Bus Service Changes
September 11, 2017
Overview- OCTA Receives Grant for Pedestrian and Bicycle Safety Program
- Board Sets Plan for Using State Transportation Funds
- Market Conditions Highlight Challenges in Delivering Projects
August 28, 2017
Overview- August Employees of the Month Honored
- Workshop Explores Managed Lanes
- OCTA Issues RFP for Toll Lane Integrator Services
- Board Receives Regional Rail Quarterly Report
August 14, 2017
Overview- $3.1 Million Awarded to Improve O.C. Water Quality
- I-405 Improvement Project Hits Milestones
- Active Transportation in O.C.
- Chairman Hennessey Reports Board’s Strategic Initiatives on Track
July 24, 2017
Overview- July Employees of the Month Honored
- Transit Master Plan Moves Forward Identifying Key Corridors
- Public Outreach to Begin on 2017-18 Bus Service Improvement Plan
July 10, 2017
Overview- Board Recognizes OCTA’s 2017 High School Interns
- OC Active Transportation Plan Underway
- Board Hears Update on SB 1 - The Road Repair and Accountability Act of 2017
June 26, 2017
Overview- $627 Million TIFIA Loan gets Board Approval for I-405 Project
- June Employees of the Month Honored
- New Members Chosen for Taxpayer Oversight Committee
- Special Needs Advisory Committee Annual Update
- Citizens Advisory Committee Annual Update and New Members Appointed
June 12, 2017
Overview- Board OKs balanced budget of $1.2 billion
- The Measure M2 quarterly progress update
- Environmental Cleanup Allocation Committee Members selected
- Environmental Oversight Committee members are appointed
- Goals set for Long-Range Transportation Plan
May 22, 2017
Overview- May Employees of the Month Honored
- OCTA Roadeo Team Honored for Achievements at International Event
- OC Bus 360° Showing Positive Results
- OC Streetcar Reaches Another Milestone
May 8, 2017
Overview- Board Receives CEO’s 1st Quarter Initiatives Update
- Caltrans Provides Update on I-5/El Toro Road Project
- Workshop Details Proposed 2017-18 Budget
April 24, 2017
Overview- April Employees of the Month Honored
- OC Fair Express to Return for 2017, 2018 Seasons
- Bus Service Changes Coming in June
- Measure M Delivering on Promises to O.C. Voters
- Board Receives Paratransit Service Overview
April 10, 2017
Overview- Board Allocates $35 Million to Help Alleviate O.C. Traffic
- Winterbottom Takes Oath of Office
- Anaheim Canyon Metrolink Station Improvements Move Forward
- Measure M Delivering on Promises to O.C. Voters
- Board Receives Paratransit Service Overview
March 27, 2017
Overview- Winterbottom Reappointed as Public Member to Board
- March Employees of the Month Honored
- Day Pass Promotion Ends April 9
- OC Streetcar Rolls Forward with Organizational Model
- Report Summarizes State of OC Transit
- Board Receives Update on Program Delivery in a Changing Market
March 13, 2017
Overview- Angels Express on Track for Two More Years
- OCTA Signal Synch Program Saves Time and Money
- Water Quality Projects on Tap through Measure M
February 27, 2017
Overview- Board Recognizes Employees of the Month for February
- OCTA Explores Transportation Technology Solutions
February 13, 2017
Overview- Employees of the Year for 2016 honored
- Grant Approved to Fund 10 Hydrogen Fuel Cell Buses
- Working to Improve Central Harbor Corridor
- CEO Johnson Announces 2017 Initiatives to Support Board Strategies
January 23, 2017
Overview- Board Recognizes Employees of the Month for January
- OCTA Board Strategic Initiatives Announced
- OC Streetcar Project Takes the Right-of-Way in Santa Ana
- Board Receives Plans for OC Bus 360° Next Steps
January 9, 2017
Overview- OCTA’s Newest Board Members Take Oath of Office
- Year-end Report Summarizes 2016 Accomplishments members
- Active Transportation Projects Receive Funding
November 28, 2016
- Employees of the month for November honored
- Board OKs Revised OC Streetcar Stop Design
- Fare Policy Changes Aim to Boost Ridership and Improve Efficiency
- O.C Wilderness Preservation Plan Approved
- Board receives CEO’s third quarter initiatives update
November 14, 2016
- I-405 Improvement Project Awarded a $1.2 billion Contractor for Its Design-Build
- Board Approves Nearly $500,000 to Continue Improvements in Active Transportation
- Measure M Forecast Revenue is Less Than Anticipated
- Measure M Aims to Keep Its’ Promises to Voters
October 24, 2016
- Employees of the month for September honored
- OCTA Awarded Grant for Purchasing Low-Emission Engines
- Metrolink Weekend Ridership in Orange County is on the Rise
October 10, 2016
- El Toro Road Interchange Project Heads into Environmental Phase
- OCTA Keeps Active Transportation Program Rolling
September 26, 2016
- Employees of the month for September honored
- Community provides feedback on proposed fare policy changes
- 405 Express Lanes procurement options discussed
September 12, 2016
- $3 million awarded to improve Orange County’s water quality
- Major bus service changes coming to Orange County Oct. 9
- Options to address reduction in bus program revenue discussed
- Board receives M2020 Plan update
August 22, 2016
- Board approves $19.5 million to improve biking, walking in O.C.
- $40 million OK’d to help ease traffic through Measure M
- Board receives Measure M performance assessment
August 8, 2016
- Board approves $19.5 million to improve biking, walking in O.C.
- $40 million OK’d to help ease traffic through Measure M
- Board receives Measure M performance assessment
July 25, 2016
- Employees of the month for July honored
- Nearly 450 miles of street lights in synch
- Board approves revised OC Streetcar funding plan
- Alternative added to SR-55 Improvement Project
June 27, 2016
- June Employees of the Month Honored
- Placentia Metrolink Commuter Rail Station Moves Forward
- ARC Planning Rolls into Harbor Boulevard Transit Study with OCTA Lead
June 13, 2016
- OCTA board approves $1.16 billion balanced budget
- $26.7 million headed to local transit shuttles
- New members selected for Measure M Taxpayers Oversight Committee
- OCTA puts Tustin on path to adding downtown bike lanes
May 23, 2016
- Employees of the month for May honored
- Orange County Fair Express Service returns in July
- Mobile ticketing closer to getting onboard
- Orange transit center parking structure moves forward with cooperative agreement
- Initial I-405 toll policy and preliminary finance plan approved
May 9, 2016
- Bus service changes coming in June
- I-405 Improvement Project moves forward with cooperative agreements
- Fare policy study results presented
April 25, 2016
- Employees of the month for April honored
- Measure M keeps its promises to voters for 25th year
- Board receives vanpool program update
- OC Streetcar project rolls forward
- Preliminary Traffic and Revenue Forecast for the 405 Express Lanes
April 11, 2016
- Millions from Measure M Awarded to Alleviate Traffic Countywide
- Freeway Service Patrol Firms Selected
- Pacific Coast Highway Corridor Study Completed
March 28, 2016
- Employees of the month for March honored
- OC Streetcar project reaches major milestones
- Next step taken in I-405 Improvement Project
- Senior Mobility Program guidelines revised
- Construction management firm selected for Passing Siding Project
- Mobile ticketing closer to fruition
March 14, 2016
- OCTA receives grant for active transportation plan
- Bus service added to Angels Express lineup
- OCTA offering $20 million for bikeway projects
- Board approves cooperative agreements with cities for I-405 Improvement Project
- Board receives quarterly Measure M update
February 22, 2016
- Employees of the Month for February honored
- Quarterly Transit Update Shows Safety on Target
- 2016 Bus Service Plan approved
- CEO Johnson announces 2016 initiatives to support board strategies
February 8, 2016
- Employees of the Year for 2015 honored
- Board receives capital programs update
- Call for projects aims to improve water quality
- Board reviews 2015 accomplishments
January 25, 2016
- Board recognizes Employees of the Month for January
- OCTA board strategic initiatives announced
- Board receives OC Bus 360° update
- Harbor Corridor Study nears end of phase one
January 11, 2016
- New OCTA Board Chair and Vice Chair appointed
- Year-end Report Summarizes 2015 Accomplishments
- OCTA to Participate in Hydrogen Fuel Cell Electric Bus Demonstration