SR-55 (I-405 to I-5) Improvement Project

Construction Updates

OCTA, in cooperation with Caltrans, is improving 4 miles of SR-55 between I-405 and I-5. The project will add one regular lane and one carpool lane in each direction, as well as merge lanes between several interchanges.

Project Details

SR-55 is a vital north-south freeway that links central Orange County and beyond to the coastal region. More than 260,000 vehicles use this stretch of SR-55 every day, and that number is expected to grow to nearly 275,000 vehicles by 2040. To address this demand, OCTA and Caltrans are working together to deliver improvements to SR-55 between I-405 and I-5.

roadway
  • Add one regular lane and one carpool lane in each direction between I-405 and I-5
  • Relocate local streets or narrow the width of some surface streets
structure
  • Improve four freeway bridges over MacArthur Boulevard, Dyer Road, Edinger Avenue and a railroad crossing
  • Build one sound wall near the SR-55/I-5 interchange and construct retaining walls throughout the corridor
  • Reconfigure on- and off-ramps
operational
  • Restripe regular lanes
  • Restripe carpool lanes for continuous access, making it easier for motorists to enter and exit the lanes
  • Add new merge lanes on northbound SR-55 between MacArthur Boulevard and Edinger Avenue
  • Install overhead signs and lighting
details
Length

4 miles

Corridor Cities

Irvine, Santa Ana and Tustin

Total estimated cost

$505.7 million

Schedule

August 2022 to 2027

WHAT: Crews are preparing to demolish and reconstruct the center median of SR-55 between I-405 and I-5 to accommodate a new carpool lane. As part of this work, crews will shift northbound SR-55 traffic onto newly constructed lanes. Intermittent nighttime lane and ramp closures will be required.

PERMANENT ON-RAMP CHANGE
As part of the traffic shift, the northbound McFadden Avenue on-ramp will be permanently restriped.

Once the new striping is in place, motorists using this on-ramp will only be able to access northbound I-5. Access to northbound SR-55 or southbound I-5 will no longer be available from this on-ramp. Motorists traveling to northbound SR-55 or southbound I-5 should use alternate routes.

This regional improvement will reduce congestion and delays by eliminating the weaving and merging near the SR-55/I-5 interchange. Motorists traveling on northbound SR-55 will still be able to merge right to access the northbound and southbound I-5 connectors.

Motorists using the McFadden Avenue on-ramp will only be able to access the northbound I-5 connector and must use alternate routes to access northbound SR-55 or southbound I-5.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

WHEN: 9 p.m. to 5 a.m. nightly, beginning as early as Monday, Oct. 26 and continuing for approximately two weeks.

 

Alternate Routes to NB SR-55 and SB I-5

To access northbound SR-55: Take Newport Avenue to the northbound I-5 ramp and stay in the right lane to access the northbound SR-55 connector.

To access southbound I-5: Take Newport Avenue to Nisson Road and turn right, then turn left on Red Hill Avenue and turn right to access the southbound I-5 on-ramp.

Southbound SR-55 Dyer Road Loop Off-Ramp Extended Closure

what:

Crews are expected to reconstruct the southbound (SB) SR-55 Dyer Road loop off-ramp, which will require an extended closure of the ramp as well as the inside lane on the SB SR-55 Dyer Road on-ramp.

when:

The off-ramp and inside lane are expected to close as soon as 9 p.m., Tuesday, Oct. 13 and reopen to motorists by 9 p.m., Friday, Oct. 23.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Retaining Wall and Bridge Construction

The SR-55 Improvement Project includes bridge reconstruction at MacArthur Boulevard, Edinger Avenue, Dyer Road, and Railroad. Remaining construction activities include utility work, safety barrier installation, roadway paving and striping. All remaining activities are expected to be completed by the end of 2026.

The project also included the construction of 18 retaining walls and 1 sound wall and surface finishing work at various retaining walls is ongoing. All retaining wall work is expected to be completed by the end of 2026.

wall design
railroad bridge

Construction Closures & Detours

Closures and detours for the SR-55 Improvement Project

Social Media Feed



Latest Activity

Yellow alert within a circle
pdf
Yellow alert within a circle
pdf
Yellow alert within a circle
pdf
Yellow alert within a circle
pdf

Contact the SR-55 Community Outreach Team

If you have questions or would like to request information in another language, please contact the Outreach Team at (888) 371-2555 or email SR55Info@octa.net.

Text "55FWYProject" to (877) 587-3065 to receive text alerts.