I-5 (I-405 to SR-55) Improvement Project
Construction Updates
Ensure you have the latest information on construction activities and project milestones delivered directly to your inbox. Use the Stay Informed form to subscribe to our project notifications, which will begin once construction is underway. If you require further assistance, please contact our community outreach team—we are ready to assist you.
Click to download to view and print a detailed list of closures and detours.

Culver Drive Bridge Work


Construction activities are expected to take place at the Culver Drive/I-5 Bridge for bridge widening activities including cast-in-drilled-hole (CIDH). In order to carry out this work, long-term closures of the lane closest to the median in both directions of Culver will be necessary.
Long-Term Lane Closures Implementation: Week of Nov. 30 (weather permitting). A nighttime full road closure is expected.
CIDH Work: Tentatively, winter 2027. Nighttime full lane closures are expected.
Daytime Work: As early as 7 a.m. to 4 p.m.
Nighttime Work: As early as 10 p.m. to 5 a.m.
24/7 Long-Term Lane Closures: Crews will place concrete barriers along the eastbound (EB) and westbound (WB) lane closest to the median and close them off in both directions of Culver at the I-5 bridge. At least one lane in each direction will be open to traffic at all times, unless otherwise specified. The lane closures are anticipated to remain in place through winter 2027 to support additional I-5 widening work.
Nighttime freeway lane and ramp closures as well as full street closures will occur intermittently. At least one lane in each direction will remain open at all times, unless otherwise noted.
Construction Closures & Detours
View the latest project closures and detours using the interactive map below.
Social Media Feed
Latest Activity
- UPDATE: Sand Canyon Pile Installation Alert
As of Oct. 14, 2026 - As of Oct. 9, 2026
- Sand Canyon Pile Installation Alert
As of Oct. 8, 2026 - As of Oct. 2, 2026
- As of Sept. 25, 2026
- Peters Canyon Drainage Demolition Alert
As of Sept. 22, 2026 - As of Sept. 21, 2026
- As of Sept. 18, 2026
- As of Sept. 14, 2026
- As of Sept. 11, 2026
- As of Sept. 4, 2026
- As of Aug. 28, 2026
- As of Aug. 26, 2026
- As of Aug. 21, 2026
- As of Aug. 19, 2026
- As of Aug. 14, 2026
- As of Aug. 7, 2026
- As of July 31, 2026
- As of July 24, 2026
- As of July 20, 2026
- As of July 17, 2026
- As of July 13, 2026
- As of July 10, 2026
- As of July 7, 2026
- As of July 2, 2026
- As of June 26, 2026
- As of June 22, 2026
- As of June 19, 2026
- As of June 12, 2026
- As of June 5, 2026
- As of June 2, 2026
- As of May 29, 2026
- As of May 22, 2026
- As of May 15, 2026
- As of May 8, 2026
- As of May 1, 2026
- As of April 24, 2026
- As of April 17, 2026
- As of April 10, 2026
- As of April 3, 2026
- As of April 1, 2026
- As of March 27, 2026
- As of March 20, 2026
- As of March 13, 2026
- As of Feb. 27, 2026
- As of Feb. 13, 2026
- As of Feb. 10, 2026
Photo Gallery
Crews performing drilled foundation work to support the I-5 bridge construction.
Crews are assembling reinforcing steel cages for bridge foundation construction beneath the I-5 bridge
Aerial photos of project area
Aerial photos of project area
I-5/Peters Canyon Hiking & Riding Trail
Jamboree and SR-261 Bridges at I-5
Segment 1
Segment 2





