I-405 Improvement Project

Translated pages

Construction Updates

OCTA in cooperation with Caltrans is improving 16 miles of the San Diego Freeway (I-405) between State Route 73 (SR-73) and Interstate 605 (I-605). It also will construct the 405 Express Lanes from SR-73 to I-605. The new express lanes – incorporating the existing carpool lanes and connectors that opened in 2014 – will be two lanes in each direction.

View Closures & Detours:  Spreadsheet icon  pdf iconPDF format

Interstate 405 Improvement Project logoOC Go Local Tax Dollars at Work

Bridge Milestones

The bridges highlighted below have recently reached a significant project milestone.

Warner Avenue Bridge

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge
  • Man walking on sidewalk New westbound sidewalk

Heil Avenue Pedestrian Bridge

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge
  • Man walking on sidewalk LED lighting for nighttime use

Westminster Boulevard

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge
  • Man riding a bike New bike lanes on both sides of the bridge
  • Man walking on sidewalk New westbound sidewalk

Fairview Road

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge

Edinger Avenue

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge
  • Man walking on sidewalk New westbound sidewalk
  • Man riding a bike New bike lanes on both sides of the bridge

Edwards Street

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge

Magnolia Street

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Two new lanes of travel
  • Man riding a bike New bike lanes on both sides of the bridge
  • Man walking on sidewalk New northbound sidewalk

Talbert Avenue

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Two new lanes of travel
  • Man riding bike New bike lanes on both sides of the bridge

McFadden Avenue

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Two new lanes of travel
  • Man riding bike New bike lanes on both sides of the bridge
  • Man walking on sidewalk New eastbound sidewalk

Bushard Street

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge

Slater Avenue

  • Completed project Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge

Brookhurst Street

  • Phase 1 Complete Complete

Improvements

  • Arrows facing opposite directions Newly improved bridge
  • Man riding a bike New bike lanes on both sides of the bridge

Bolsa Avenue

  • Phase 1 Complete Complete

Improvements

  • Arrows facing opposite directions Two new lanes of travel
  • Man riding a bike New bike lanes on both sides of the bridge
  • Man walking on sidewalk New westbound sidewalk

Bolsa Chica Road

  • Phase 1 Complete Complete

Improvements

  • Arrows facing opposite directions Four new lanes of travel
  • Man riding a bike New bike lanes on both sides of the bridge

Goldenwest Street

  • Phase 1 Complete Complete

Improvements

  • Arrows facing opposite directions Three new lanes of travel
  • Man riding a bike New bike lanes on both sides of the bridge
  • Man walking on sidewalk New southbound sidewalk

Latest Activity

Blue pdf icon
Weekly Construction Alert
Weekly Construction Alert
Monday, November 27, 2023
Yellow alert within a circle
Closures and Detours
Closures and Detours
Monday, November 20, 2023
Yellow alert within a circle
Closures and Detours
Closures and Detours
Thursday, November 2, 2023
Yellow alert within a circle
closures and detours
Yellow alert within a circle
Closures and Detours
Closures and Detours
Wednesday, October 18, 2023
Yellow alert within a circle
Closures and Detours
Closures and Detours
Wednesday, October 18, 2023
Yellow alert within a circle
Closures and Detours
Closures and Detours
Thursday, October 12, 2023
Yellow alert within a circle
Closures and Detours
Closures and Detours
Wednesday, October 11, 2023
Green checkmark in a green circle
Milestones and Updates
Milestones and Updates
Monday, May 15, 2023

Contact the 405 Community Outreach Team

If you have questions, please contact the Outreach Team by calling (888) 400-8994.

Para obtener más información sobre el Proyecto de Ampliación en el I-405, llame al (888) 400-8994.

Để biết thêm thông tin về Dự Án Cải Thiện Xa Lộ I-405, xin vui lòng liên lạc cô Gia Lý theo đường dây tiếng Việt (888) 662-6569.

/media/fsmgoz2v/405-freeway-collage.jpg
/media/nchbfu21/405-freeway-collage-mobile.jpg