Rail Projects - Detectable Tile Replacement Project

Skip navigation Reduce Motion High Contrast Careers Contact Us
Skip to main content
  • Detectable Tile Replacement Project

    Project Contact 1 of 1
    Detectable Tile Replacement Project

    OCTA, in coordination with Metrolink, will upgrade safety features at six stations in Orange County. Improvements will include removal and replacement of aging yellow detectable warning tiles and other directional tiles, as well as restriping of stations platforms. Six stations will receive these upgrades: Buena Park, Fullerton, Orange, Santa Ana, Laguna Niguel/Mission Viejo, and San Clemente.”

    Buena Park Station

    Crews will work to enhance safety features at the Buena Park Station starting Monday, January 11, 2021, for approximately four weeks. During construction, crews will remove and replace aging yellow detectable warning tiles and directional tiles from the station platform. Crews will also restripe pedestrian markings along the platform.

    Orange Station

    Construction is anticipated to begin early February 2021.

    Santa Ana Station

    Construction is anticipated to begin late February 2021.

    Laguna Niguel/Mission Viejo Station

    Construction is anticipated to begin early April 2021.

    San Clemente Station

    Construction is anticipated to begin late April 2021.

    Fulleron Station

    Construction is anticipated to begin early May 2021.

    Overview
    Detectable Tile Replacement Project

    OCTA, in coordination with Metrolink, will upgrade safety features at six stations in Orange County. Improvements will include removal and replacement of aging yellow detectable warning tiles and other directional tiles, as well as restriping of stations platforms. Six stations will receive these upgrades: Buena Park, Fullerton, Orange, Santa Ana, Laguna Niguel/Mission Viejo, and San Clemente.”

    Construction

    Buena Park Station

    Crews will work to enhance safety features at the Buena Park Station starting Monday, January 11, 2021, for approximately four weeks. During construction, crews will remove and replace aging yellow detectable warning tiles and directional tiles from the station platform. Crews will also restripe pedestrian markings along the platform.

    Orange Station

    Construction is anticipated to begin early February 2021.

    Santa Ana Station

    Construction is anticipated to begin late February 2021.

    Laguna Niguel/Mission Viejo Station

    Construction is anticipated to begin early April 2021.

    San Clemente Station

    Construction is anticipated to begin late April 2021.

    Fulleron Station

    Construction is anticipated to begin early May 2021.

    Detours